Project update on our scheme at Charterhouse School, for 2 new boarding houses.
Works on the north block are progressing well, the
R.C Frame is complete up to the 3rd floor. The internal blockwork at ground floor level is well advanced and on the first floor the blockwork has just commenced on site.
Whilst on the south block the R.C frame complete up to the second floor and brickwork has started on the ground floor.