Project Update: Rose Hill, Oxford

Progress update on our site at Rose Hill in Oxford, for 43 new apartments.
Block A is ready for the second floor slabs, plus we are currently installing the brick and blockwork on the second floor on block B.
 
The site is due for completion June 2021

Project Update: Charterhouse School

Project update on our scheme at Charterhouse School, for 2 new boarding houses.
Works on the north block are progressing well, the
R.C Frame is complete up to the 3rd floor. The internal blockwork at ground floor level is well advanced and on the first floor the blockwork has just commenced on site.
Whilst on the south block the R.C frame complete up to the second floor and brickwork has started on the ground floor.