Thames Valley Police Headquarters, Kidlington

Project Info

  • Construction Date

    September 2014

  • Category

    Other

  • Value

    1.7M

  • Duration

    35 weeks

Refurbishment of Police Headquarters

Works comprised of the refurbishment to the main block of the Thames Valley Police Headquarters, this involved re-planned layout and reconfiguration to the offices and reception areas, including the refurbishment to the external façade.

A new replacement heating systems was installed, as well as the upgrade to mechanical and electrical services.

External improvements works to the fabrics were involved, this included the removal of  the lightweight roof structure and re-roofing works, as well as stainless steel cladding panels, creating a curtained feature wall.

There were works to the data centre, to provide energy efficient cooling and some minor external landscaping, as well as new internal finishes.

The works were undertaken whilst the building and adjacent areas on the site remained operational.