Houndmills Trade Park, Basingstoke
Works started with the demolition of the existing building which stood on the site, followed by the construction of 5 new trade warehouse units, together with all associated external works, drainage and services.
After completion of this project Feltham were awarded with the works for the next phase of the trading estate, erecting 2 units to be used for retail (pictured below)